SUSE QA tests - Milestone 30

about 15 months late (2020-01-10)

88%

256 issues   (222 closed34 open)

SUSE QA tests - Milestone 31

about 14 months late (2020-02-21)

77%

70 issues   (48 closed22 open)

SUSE QA tests - Milestone 32

about 12 months late (2020-04-03)

78%

25 issues   (21 closed4 open)

SUSE QA tests - Milestone 33

about 11 months late (2020-05-15)

96%

23 issues   (22 closed1 open)

SUSE QA tests - Milestone 35+

about 10 months late (2020-06-26)

future milestone for longterm planning

80%

34 issues   (24 closed10 open)

SUSE QA tests - SLE 15 SP3

Due in 19 days (2021-05-01)

All tickets being scheduledin scope of SLE 15 SP3, no clear date yet

84%

289 issues   (236 closed53 open)

QE Kernel - QE Kernel Done

Kernel/Filesystem/HPC done tasks

100%

770 issues   (769 closed1 open)

QA - QE-Core: Ready

Used by QE Core to track sprint items

29%

19 issues   (5 closed14 open)

openQA Project - Ready

Next tasks to be picked up by the QE tools team

86%

524 issues   (434 closed90 open)

QA - future

a "virtual" milestone that is never reached. Everything that is currently out of scope can go here. Place for new feature ideas, wishes, proposed improvements and changes which we could work on in the future but are not currently planned for.

51%

1043 issues   (513 closed530 open)