SUSE QA tests - Milestone 30

about 7 months late (2020-01-10)

80%

222 issues   (174 closed48 open)

SUSE QA tests - Milestone 31

about 6 months late (2020-02-21)

66%

70 issues   (40 closed30 open)

SUSE QA tests - Milestone 32

about 4 months late (2020-04-03)

62%

25 issues   (20 closed5 open)

SUSE QA tests - Milestone 33

about 3 months late (2020-05-15)

96%

23 issues   (22 closed1 open)

SUSE QA tests - Milestone 35+

41 days late (2020-06-26)

future milestone for longterm planning

68%

34 issues   (21 closed13 open)

SUSE QA tests - Planned - kernel&network

37 days late (2020-06-30)

Plans for upcoming sprint

18%

98 issues   (8 closed90 open)

SUSE QA tests - doing board - kernel

20 days late (2020-07-17)

18%

17 issues   (2 closed15 open)

SUSE QA tests - SLE 15 SP3

Due in about 9 months (2021-05-01)

All tickets being scheduledin scope of SLE 15 SP3, no clear date yet

43%

74 issues   (29 closed45 open)

SUSE QA tests - Done - kernel&network

100%

633 issues   (632 closed1 open)

QA - future

a "virtual" milestone that is never reached. Everything that is currently out of scope can go here. Place for new feature ideas, wishes, proposed improvements and changes which we could work on in the future but are not currently planned for.

53%

798 issues   (408 closed390 open)