Project

General

Profile

Actions

action #32086

closed

coordination #31426: [sle][functional][u][epic] extend tests for icewm regarding raspberry pi scenario (was: extend tests for icewm a bit)

[sle][functional][u][icewm][raspi][easy] Check that boot/start works as expected

Added by SLindoMansilla almost 7 years ago. Updated almost 5 years ago.

Status:
Rejected
Priority:
Low
Assignee:
-
Category:
New test
Target version:
Start date:
2018-02-21
Due date:
% Done:

0%

Estimated time:
Difficulty:
easy

Description

Acceptance criteria

  • AC: openQA tests cover login in and out with xdm, reboot, and shutdown.

Tasks

  1. Create a test module to cover the acceptance criteria.
  2. The test asserts booting to xdm.
  3. The test asserts login in with xdm to IceWM session.
  4. The test asserts login out from IceWM session to xdm.
  5. The test asserts rebooting works.
  6. The test asserts shutdown works.

Related issues 1 (0 open1 closed)

Related to openQA Tests (public) - action #32068: [sle][functional][u]icewm - reboot and shutdown testRejected2018-02-21

Actions
Actions #1

Updated by SLindoMansilla almost 7 years ago

  • Target version set to Milestone 15
Actions #2

Updated by SLindoMansilla almost 7 years ago

  • Related to action #32068: [sle][functional][u]icewm - reboot and shutdown test added
Actions #3

Updated by okurz almost 7 years ago

  • Due date set to 2018-04-10
Actions #4

Updated by cwh over 6 years ago

  • Difficulty set to easy
Actions #5

Updated by okurz over 6 years ago

  • Due date deleted (2018-04-10)
  • Target version changed from Milestone 15 to Milestone 16

not enough capacity in S14, moving

Actions #6

Updated by okurz over 6 years ago

  • Subject changed from [sle][functional][icewm][raspi][easy] Check that boot/start works as expected to [sle][functional][u][icewm][raspi][easy] Check that boot/start works as expected
  • Target version changed from Milestone 16 to Milestone 17
Actions #7

Updated by okurz over 6 years ago

  • Due date set to 2018-07-17
Actions #8

Updated by okurz over 6 years ago

  • Target version changed from Milestone 17 to Milestone 17
Actions #9

Updated by okurz over 6 years ago

  • Target version changed from Milestone 17 to Milestone 18
Actions #10

Updated by okurz over 6 years ago

  • Due date changed from 2018-07-17 to 2018-08-14

It's hackweek time!

Actions #11

Updated by okurz over 6 years ago

  • Due date deleted (2018-08-14)
  • Target version changed from Milestone 18 to future

I agree with the feasibilty of this but in comparison to other tasks I would like to schedule this for now only on request from QSF team members or external stakeholders.

Actions #12

Updated by okurz about 6 years ago

  • Status changed from Workable to New

Bulk action to set status back to "New" for older tickets which are in "future". They would need to be revisited in time when we come up with a defined plan and assign to a milestone.

Actions #13

Updated by okurz almost 6 years ago

  • Priority changed from Normal to Low

let's focus more on improving our current tests and workflows first. Putting to "holding tank" :)

Actions #14

Updated by mgriessmeier almost 5 years ago

  • Status changed from New to Rejected

SLE15 on RPi/JeOS doesn't include graphical interface anymore, so nothing to do here at the moment....

Actions

Also available in: Atom PDF