Project

General

Profile

Actions

action #115181

closed

[qe-core] Prepare for ALP - Enablement of ALP for QE-Core

Added by szarate over 2 years ago. Updated 12 months ago.

Status:
Resolved
Priority:
High
Assignee:
Category:
New test
Start date:
2023-05-25
Due date:
2023-05-25
% Done:

0%

Estimated time:
Difficulty:
Sprint:
QE-Core: October Sprint (Sep 28 - Oct 26)

Description

As ALP is approaching, we should start to get on board with the train, that would allow us, and other teams to be able to integrate the ALP tests into their radars too (including openQA-tuned images, as we do already for SLES)

As for this task, what we mainly need to do is to start by creating a dedicated jobgroup on osd that mirrors openSUSE ALP (even if it means duplicating an already existing one, for now), check in with QE-C if a similar jobgroup already exists in osd.

Coordination needs to be done too with QE-Yast, to have autoyast profiles for the generation of the default images, adjustments of memory limits and HDD limits can be done at a later point.

Acceptance criteria

AC1: ALP jobgroup is mimicked on osd and both are added to the list of links of the bugbusters' review part.
AC2: All 4 flavors are enabled for the new Job Group (If one can't, it is stated in its own ticket why)
AC3: All of the jobs publish HDD images
AC4: Ticket exists for autoyast profiles for ALP/or pull requests are already created (taking #115184 into account)


Related issues 1 (0 open1 closed)

Copied to openQA Tests (public) - action #115184: [qe-core] Prepare for ALP - Move ALP test scheduling to YAMLRejectedszarate2023-05-252023-05-25

Actions
Actions #1

Updated by szarate over 2 years ago

  • Project changed from 46 to openQA Tests (public)
  • Category set to New test
Actions #2

Updated by szarate over 2 years ago

  • Description updated (diff)
Actions #3

Updated by szarate over 2 years ago

  • Copied to action #115184: [qe-core] Prepare for ALP - Move ALP test scheduling to YAML added
Actions #4

Updated by szarate over 2 years ago

  • Description updated (diff)
  • Priority changed from Normal to High

This would be the main sprint focus.

Actions #5

Updated by dvenkatachala over 2 years ago

  • Assignee set to dvenkatachala
Actions #6

Updated by szarate over 2 years ago

Carrying over to next sprint

Actions #7

Updated by szarate over 2 years ago

  • Sprint changed from QE-Core: August Sprint (Aug 03 - Aug 31) to QE-Core: September Sprint (Aug 31 - Sep 28)
Actions #8

Updated by pdostal over 2 years ago

Can you @szarate please explain why AC1 is needed?

Actions #9

Updated by dvenkatachala over 2 years ago

I have created the medium, Test suites and job group in the OSD - https://openqa.suse.de/group_overview/457.
Since no ALP builds are being built on IBS yet, will wait for the build to proceed further.

Actions #10

Updated by dvenkatachala over 2 years ago

  • Status changed from Workable to Feedback
Actions #11

Updated by JERiveraMoya over 2 years ago

As far as I could understand very recently discussing with Jose and Santi, all the development will happen in O3 and OBS
Too soon for OSD yet, right Santi?

Actions #12

Updated by szarate over 2 years ago

JERiveraMoya wrote:

As far as I could understand very recently discussing with Jose and Santi, all the development will happen in O3 and OBS
Too soon for OSD yet, right Santi?

We are planning ahead, still all of the ALP development will happen in OBS/O3.

For now main justification is availability of resources (OSD has more than O3 does), both instances have to be in sync (we'll figure out how at some point in the future) when it comes to tests being executed, at least results-wise speaking.

Actions #13

Updated by szarate over 2 years ago

Dee, can you add the jobgroup to the CI? https://gitlab.suse.de/qa-maintenance/qam-openqa-yml

Actions #14

Updated by szarate about 2 years ago

JobGrups and Testsuites created, adding them to the qam-openqa-yml

Actions #15

Updated by szarate about 2 years ago

  • Sprint changed from QE-Core: September Sprint (Aug 31 - Sep 28) to QE-Core: October Sprint (Sep 28 - Oct 26)
Actions #16

Updated by slo-gin about 2 years ago

This ticket was set to High priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.

Actions #17

Updated by slo-gin about 2 years ago

This ticket was set to High priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.

Actions #18

Updated by slo-gin almost 2 years ago

This ticket was set to High priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.

Actions #19

Updated by slo-gin almost 2 years ago

This ticket was set to High priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.

Actions #20

Updated by slo-gin almost 2 years ago

This ticket was set to High priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.

Actions #21

Updated by dvenkatachala 12 months ago

  • Status changed from Feedback to Resolved
Actions

Also available in: Atom PDF