SUSE QA tests - Milestone 30

about 15 months late (2020-01-10)

88%

256 issues   (222 closed34 open)

SUSE QA tests - Milestone 32

about 12 months late (2020-04-03)

78%

25 issues   (21 closed4 open)

SUSE QA tests - Milestone 33

about 11 months late (2020-05-15)

96%

23 issues   (22 closed1 open)

SUSE QA tests - SLE 15 SP3

Due in 19 days (2021-05-01)

All tickets being scheduledin scope of SLE 15 SP3, no clear date yet

84%

289 issues   (236 closed53 open)

QA - future

a "virtual" milestone that is never reached. Everything that is currently out of scope can go here. Place for new feature ideas, wishes, proposed improvements and changes which we could work on in the future but are not currently planned for.

51%

1043 issues   (513 closed530 open)