closed

coordination #40979: [sle][functional][y][epic] New test strategy for autoyast profiles from ay-tests repo

[functional][y] Test pipeline using openQA for autoyast related changes before they hit the product

Added by okurz over 5 years ago. Updated 3 months ago.

Status:
Rejected
Priority:
Normal
Assignee:
-
Target version:
Start date:
2018-10-11
Due date:
% Done:

0%

Estimated time:

Description

Motivation

To ease integration-/systemtests based on openQA for development teams we should provide a proof-of-concetp of a test pipeline that shows how code in e.g. PRs or SRs is picked up, tested within the context of openQA and test results are fed back to the creators of the PR/SR

Actions #1

Updated by riafarov over 4 years ago

  • Due date set to 2020-12-15
Actions #2

Updated by okurz over 2 years ago

This ticket had a due set but exceeded it already by more than 14 days. We would like to take the due date seriously so please update the ticket accordingly (resolve the ticket or update the due-date or remove the due-date). See https://progress.opensuse.org/projects/openqatests/wiki/Wiki#SLOs-service-level-objectives for details. This update was done as agreed within the SUSE QE Sync call 2021-09-01

Actions #3

Updated by okurz over 2 years ago

  • Due date deleted (2020-12-15)
Actions #4

Updated by slo-gin over 1 year ago

This ticket was set to Normal priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.

Actions #5

Updated by JERiveraMoya 3 months ago

  • Status changed from New to Rejected

Backlog clean-up.

Actions