Optimize test coverage for default module (base) in migrations from SLE 12 SP5

Added by leli 10 months ago. Updated 9 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
Start date:
2023-06-20
Due date:
% Done:

0%

Estimated time:

Description

Motivation

we are doing changes to the distri of modules but also moving to Migration job group or considering other factors, update test matrix to reduce the number of test suite run in openQA while keeping/improving (distributing better) the test coverage for migration.

We need add/modify some base module migration test on SLES12SP5 refer to test matrix

The test need to be added as below:
migration daily job group(https://openqa.nue.suse.com/group_overview/265)

  • offline_sles12sp5_pscc_def_full@aarch64
  • offline_sles12sp5_media_all_full@aarch64
  • offline_sles12sp5_media_base_def_full@ppc64le
  • offline_sles12sp5_media_base_def_full@s390x-zvm (change from zkvm to zvm)
  • autoupgrade_sles12sp5_pscc_base_all_full_auto@s390x-kvm (move this from Migration: Milestone to Migration job group, p2 to p1, and scc-> pscc)
  • offline_sles12sp5_pscc_def_full@x86_64
  • offline_sles12sp5_media_base_all_full_lock@x86_64 (move this from Migration: Milestone to Migration job group

Acceptance criteria

AC1: Test coverage for the case when no additional product/extension (base case) are added reflects the migration matrix

Actions #1

Updated by leli 10 months ago

  • Description updated (diff)
Actions #2

Updated by JERiveraMoya 10 months ago

  • Subject changed from Add/modify some base module migration test on SLES12SP5 to Optimize test coverage for default module (base) in migrations from SLE 12 SP5
  • Description updated (diff)
  • Status changed from New to Workable
  • Target version set to Current
  • Parent task set to #130216
Actions #3

Updated by JERiveraMoya 10 months ago

  • Description updated (diff)
Actions #4

Updated by leli 10 months ago

  • Description updated (diff)
Actions #5

Updated by shukui 10 months ago

  • Assignee set to shukui
Actions #6

Updated by shukui 10 months ago

  • Status changed from Workable to In Progress
Actions #9

Updated by shukui 9 months ago

  • Status changed from In Progress to Resolved