coordination #54617
closed[functional][y][pvm][epic] Enable more scenarios to run on powerVM Backend
100%
Description
User story¶
right now, we only have two scenarios running on powerVM (ssh-x and textmode). We want to increase the coverage here.
This even means we might drop some of the cases on powerKVM or better transfer it to powerVM
this ticket follows a call with Diego, Marita, Rodion and Matthias, where we want to figure out which scenarios makes sense and with what we wanna start
Suggestions¶
Use Test Development job group and start with enabling identified scenarios listed below:
- allpatterns
- btrfs
- xfs
- ext4
Test scenario priorities can be found here: https://openqa.suse.de/tests/4084492#
Updated by mgriessmeier about 5 years ago
- Subject changed from [functional][u][y][pvm] Enable more scenarios to run on powerVM Backend to [functional][u][y][pvm][epic] Enable more scenarios to run on powerVM Backend
Updated by mgriessmeier about 5 years ago
right now those tests are enabled in test development: https://openqa.suse.de/tests/overview?arch=&modules=bootloader&modules_result=failed&distri=sle&version=12-SP5&build=0242&groupid=132#
all are failing because our default, VNC can nonet be used for installation - therefore created subtask #54689
Updated by mgriessmeier about 5 years ago
- Description updated (diff)
removed mediacheck - since it makes no sense, because we already test the medium of ppc (it's identical with KVM one)
Updated by mgriessmeier about 5 years ago
- Status changed from Workable to Feedback
- Target version changed from Milestone 26 to Milestone 27
4 default tests are enabled now in SLE12 - YaST job group:
https://openqa.suse.de/tests/3264654
https://openqa.suse.de/tests/3262265
https://openqa.suse.de/tests/3264657
https://openqa.suse.de/tests/3262264
keeping on feedback until further test enablements are agreed on
Updated by mgriessmeier about 5 years ago
- Target version changed from Milestone 27 to Milestone 28
Updated by JERiveraMoya about 5 years ago
- Due date changed from 2019-10-08 to 2019-10-22
due to changes in a related task
Updated by jlausuch about 5 years ago
- Related to action #57329: [kernel][functional] PowerVM console is not active all the time added
Updated by riafarov almost 5 years ago
- Target version changed from Milestone 28 to Milestone 30+
Updated by riafarov almost 5 years ago
- Due date changed from 2019-12-03 to 2019-12-17
due to changes in a related task
Updated by mgriessmeier almost 5 years ago
- Target version changed from Milestone 30+ to Milestone 30
bulk moved to M30 for revisiting
Updated by riafarov over 4 years ago
- Due date changed from 2020-02-25 to 2020-03-24
due to changes in a related task
Updated by riafarov over 4 years ago
- Due date changed from 2020-03-24 to 2020-04-07
due to changes in a related task
Updated by riafarov over 4 years ago
- Due date changed from 2020-04-21 to 2020-05-05
due to changes in a related task: #65864
Updated by riafarov over 4 years ago
- Due date changed from 2020-05-05 to 2020-05-19
due to changes in a related task: #65864
Updated by SLindoMansilla over 4 years ago
- Assignee changed from mgriessmeier to SLindoMansilla
Updated by riafarov over 4 years ago
- Due date changed from 2020-05-19 to 2020-06-23
due to changes in a related task: #66730
Updated by riafarov over 4 years ago
- Due date changed from 2020-06-23 to 2020-06-02
due to changes in a related task: #66730
Updated by riafarov over 4 years ago
- Target version changed from Milestone 30 to SLE 15 SP2
Updated by riafarov over 4 years ago
- Due date changed from 2020-06-02 to 2020-06-16
due to changes in a related task: #67405
Updated by riafarov over 4 years ago
- Due date changed from 2020-06-16 to 2020-06-30
due to changes in a related task: #67879
Updated by riafarov over 4 years ago
- Due date changed from 2020-06-30 to 2020-07-14
due to changes in a related task: #67882
Updated by riafarov over 4 years ago
- Due date changed from 2020-07-14 to 2020-06-30
due to changes in a related task: #67882
Updated by riafarov over 4 years ago
- Due date changed from 2020-06-30 to 2020-07-14
due to changes in a related task: #68254
Updated by riafarov over 4 years ago
- Due date changed from 2020-07-14 to 2020-07-28
due to changes in a related task: #68733
Updated by riafarov over 4 years ago
- Due date changed from 2020-07-28 to 2020-08-25
due to changes in a related task: #65304
Updated by riafarov over 4 years ago
- Target version changed from SLE 15 SP2 to SLE 15 SP3
Updated by riafarov about 4 years ago
- Due date changed from 2020-08-25 to 2020-09-08
due to changes in a related task: #65304
Updated by riafarov about 4 years ago
- Due date changed from 2020-09-08 to 2020-09-22
due to changes in a related task: #65304
Updated by riafarov about 4 years ago
- Due date changed from 2020-09-22 to 2020-10-06
due to changes in a related task: #68980
Updated by szarate about 4 years ago
- Tracker changed from action to coordination
Updated by szarate about 4 years ago
See for the reason of tracker change: http://mailman.suse.de/mailman/private/qa-sle/2020-October/002722.html
Updated by riafarov almost 4 years ago
- Project changed from openQA Tests to qe-yam
- Subject changed from [functional][u][y][pvm][epic] Enable more scenarios to run on powerVM Backend to [functional][y][pvm][epic] Enable more scenarios to run on powerVM Backend
- Category deleted (
Spike/Research) - Status changed from Feedback to In Progress
- Assignee changed from SLindoMansilla to riafarov
Assigning to myself as the only remaining item in the epic is for our team.
Updated by riafarov almost 4 years ago
- Status changed from In Progress to Closed