Actions
coordination #108797
open[qe-core] Leap setup 15.4 openqa for updates
Status:
Blocked
Priority:
Normal
Assignee:
-
Category:
Infrastructure
Target version:
Start date:
2022-05-18
Due date:
% Done:
90%
Estimated time:
(Total: 0.00 h)
Difficulty:
Sprint:
QE-Core: July Sprint (Jul 06 - Aug 03)
Description
Please setup openSUSE Leap 15.4 updates for openqa.
Same setup is 15.3.
Please set up on BOTH openqa.suse.de and openqa.opensuse.org side.
Updated by maritawerner over 2 years ago
- Subject changed from setup 15.4 openqa for updates to [qe-core] setup 15.4 openqa for updates
Updated by msmeissn over 2 years ago
- Priority changed from Normal to High
I had asked santiago to prio this
Updated by szarate over 2 years ago
- Sprint set to QE-Core: May Sprint (May 11 - Jun 08)
- Category set to Infrastructure
Updated by szarate over 2 years ago
- Related to action #72202: [qe-core] setup openSUSE Leap 15.3 openQA added
Updated by szarate over 2 years ago
- Blocks action #100038: enable openQA maintenance testing added
Updated by szarate over 2 years ago
- Blocks action #99987: Maintenance openQA setup added
Updated by szarate over 2 years ago
- Related to action #99894: add openqa upgrade tests to/from 15.3 added
Updated by szarate over 2 years ago
- Related to action #108692: [qe-core] Leap offline migration - do not skip releases (15.0 -> 15.1 -> 15.2 -> 15.3) added
Updated by mloviska over 2 years ago
- Status changed from New to In Progress
- Assignee set to mloviska
Updated by szarate over 2 years ago
- Assignee changed from mloviska to punkioudi
- Target version changed from future to QE-Core: Ready
Updated by mloviska over 2 years ago
- Related to action #91554: [qem][leap][opensuse][qe-core] Update GM images before running upgrade tests added
Updated by szarate over 2 years ago
Jobs in osd are scheduled in the devel jobgroup due to sporadic failures
Updated by szarate over 2 years ago
- Subject changed from [qe-core] setup 15.4 openqa for updates to [qe-core] Leap setup 15.4 openqa for updates
Updated by szarate over 2 years ago
- Sprint changed from QE-Core: May Sprint (May 11 - Jun 08) to QE-Core: June Sprint (Jun 08 - Jul 06)
Updated by szarate over 2 years ago
- Sprint changed from QE-Core: June Sprint (Jun 08 - Jul 06) to QE-Core: July Sprint (Jul 06 - Aug 03)
Updated by livdywan over 2 years ago
This ticket was set to High priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.
Updated by msmeissn over 2 years ago
- Copied to action #116072: [qe-core] Leap setup 15.5 openqa for updates added
Actions