[functional][y][epic] Established workflow how system level test failures found in openQA of QA validation tests can be moved to earlier testing, e.g. staging, OBS devel projects, PR, commit

Added by okurz over 4 years ago. Updated 3 months ago.

Status:
New
Priority:
Normal
Assignee:
Target version:
Start date:
2018-10-24
Due date:
% Done:

0%

Estimated time:

Description

Motivation

As a SysMgmt developer I want to benefit from the QA based tests in an earlier integration and test stage to have shorter feedback time and easier problem investigation


Related issues

Related to openQA Project - action #18000: [dashboard] Better integration of status from external jobs and testing systemsWorkable2017-03-24

History

#1 Updated by okurz over 4 years ago

  • Target version set to Milestone 23

#2 Updated by okurz over 4 years ago

  • Due date set to 2019-03-26

#3 Updated by okurz over 4 years ago

  • Related to action #18000: [dashboard] Better integration of status from external jobs and testing systems added

#4 Updated by JERiveraMoya about 4 years ago

  • Due date changed from 2019-03-26 to 2019-04-09

#5 Updated by riafarov about 4 years ago

  • Target version changed from Milestone 23 to Milestone 24

#6 Updated by riafarov about 4 years ago

  • Due date deleted (2019-04-09)
  • Assignee set to riafarov

We need to schedule sub-tasks for this one. Removing from the sprint backlog.

#7 Updated by riafarov about 4 years ago

  • Target version changed from Milestone 24 to Milestone 25

#8 Updated by riafarov almost 4 years ago

  • Target version changed from Milestone 25 to Milestone 27

Still not there.

#9 Updated by mgriessmeier over 3 years ago

  • Target version changed from Milestone 27 to Milestone 28

#10 Updated by riafarov over 3 years ago

  • Target version changed from Milestone 28 to future

#11 Updated by riafarov over 3 years ago

  • Parent task deleted (#40475)

Not related to the team split, so removing parent ticket.

#12 Updated by szarate over 2 years ago

  • Tracker changed from action to coordination

#14 Updated by riafarov over 2 years ago

  • Project changed from openQA Tests to qe-yam
  • Category deleted (Enhancement to existing tests)

#15 Updated by riafarov about 2 years ago

  • Assignee changed from riafarov to oorlov

#16 Updated by oorlov over 1 year ago

  • Assignee changed from oorlov to JERiveraMoya

#17 Updated by slo-gin 3 months ago

This ticket was set to Normal priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.