Actions
coordination #37910
closedcoordination #121720: [saga][epic] Migration to QE setup in PRG2+NUE3 while ensuring availability
coordination #129280: [epic] Move from SUSE NUE1 (Maxtorhof) to new NBG Datacenters
[tools][epic] Migration of or away from qanet.qa.suse.de
Start date:
2018-06-29
Due date:
% Done:
100%
Estimated time:
(Total: 0.00 h)
Description
qanet is an SLES11SP0 and needs a newer replacement to be safe for the future.
Replacement hardware¶
1. Physical machine¶
General advantages:¶
- Potentially less problems then a virtualized machine (less layers -> less problems (especially in the network world))
General disadvantages:¶
- Less flexible then a virtual machine
1.1. Use the same machine as qanet runs on¶
Advantages:¶
- No new hardware needed
- qanet is a quad core with 6GB of RAM -> More then sufficient for a network management server
Disadvantages:¶
- Downtime for the whole network while migrating
- In-place upgrade from SLE11 up to SLE15 might render the system unusable and then requires a re-installation
- No (fast) way back in case of major issues after upgrading
- Hardware of the server is long out-of-service
1.2. Buy new hardware¶
Advantages:¶
- Parallel setup with already running qanet possible
- After initial setup and migration, a fail-over setup is possible
- Fallback in case of major issues after migration should be easily possible (unplug new, plugin old)
- Hardware service for at least 2-3 years
Disadvantages:¶
- Investment needed
2. Virtual machine¶
General advantages¶
- More flexible in the future (VMs can be moved to other hosts, easy backup, failover easily possible)
General disadvantages¶
- Setup of hypervisor can influence the functionality of network server
User qamaster.qa.suse.de as VM host¶
Advantages:¶
- Already exists
Disadvantages:¶
- Already close to it's capacity limit (renegotiation with users (of qamaster) needed)
- Also the hypervisor OS needs an upgrade (SLES12)
Updated by nicksinger about 6 years ago
- Subject changed from [labs] Preparing the migration of qanet.qa.suse.de to [labs][epic] Preparing the migration of qanet.qa.suse.de
Updated by szarate almost 4 years ago
- Tracker changed from action to coordination
Updated by szarate almost 4 years ago
See for the reason of tracker change: http://mailman.suse.de/mailman/private/qa-sle/2020-October/002722.html
Updated by okurz over 1 year ago
- Subject changed from [labs][epic] Preparing the migration of qanet.qa.suse.de to [tools][epic] Preparing the migration of qanet.qa.suse.de
- Target version set to future
Updated by okurz over 1 year ago
- Tags set to infra, qanet, maxtorhof, nue1, dhcp, dns, pxe
- Subject changed from [tools][epic] Preparing the migration of qanet.qa.suse.de to [tools][epic] Migration of qanet.qa.suse.de
- Category set to Infrastructure
Updated by okurz about 1 year ago
- Related to action #132623: Decommissioning of selected selected LSQ QE machines from NUE1-SRV2 added