action #133364

closed

QA - coordination #121720: [saga][epic] Migration to QE setup in PRG2+NUE3 while ensuring availability

QA - coordination #123800: [epic] Provide SUSE QE Tools services running in PRG2 aka. Prg CoLo

Migration of o3 VM to PRG2 - Decommission old-ariel in NUE1 as soon as we do not need it anymore

Added by okurz 10 months ago. Updated 6 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
Category:
-
Target version:
Start date:
Due date:
% Done:

0%

Estimated time:
Tags:

Description

Motivation

The openQA webUI VM for o3 was moved to PRG2 but for now is still relying heavily on ressources from NUE1, e.g. workers, bare-metal machines, s390x, powerpc, aarch64 as well as OBS ressources. As soon as we have alternatives for all not relying on NUE1 we should decommission old-ariel

Acceptance criteria

  • AC1: o3 openQA jobs run successfully for all four archs x86_64+aarch64+s390x+ppc64le without relying on old-ariel
  • AC2: o3 multi-machine jobs run successfully on o3 without relying on old-ariel
  • AC3: o3 openQA bare-metal tests run successfully without relying on old-ariel

Suggestions

  • Wait for all related blocking tasks #132134 #100455 #132140 #132143 #132152 #132617 #137408
  • Ensure o3 openQA jobs run successfully for all four archs x86_64+aarch64+s390x+ppc64le without relying on old-ariel
  • Ensure o3 multi-machine jobs run successfully on o3 without relying on old-ariel
  • Ensure o3 openQA bare-metal tests run successfully without relying on old-ariel
  • As soon as we do not need the rsync+ssh tunnel to old-ariel anymore (after OBS to PRG2 migration) enforce apparmor for webUI process on new-ariel and monitor
  • Ask Eng-Infra to decommission old-ariel for good

Related issues 5 (0 open5 closed)

Related to openQA Infrastructure - action #137408: Support move of s390x mainframe(s) to PRG2 - o3 size:MResolvedmgriessmeier2023-06-29

Actions
Related to openQA Infrastructure - action #150956: o3 cannot send e-mails via smtp relay size:MResolvedokurz2023-11-16

Actions
Copied from openQA Infrastructure - action #132143: Migration of o3 VM to PRG2 - 2023-07-19 size:MResolvednicksinger2023-06-29

Actions
Copied to openQA Infrastructure - action #134822: Migration of osd VM to PRG2 - Decommission old-osd in NUE1 as soon as we do not need it anymore size:MResolvedokurz2023-08-30

Actions
Copied to openQA Infrastructure - action #135191: Migration of o3 VM to PRG2 - Use direct zabbix connection size:MResolveddheidler

Actions