Project

General

Profile

Actions

action #95338

open

[qe-core] Why version specific job groups for "Maintenance - QR"?

Added by okurz almost 3 years ago. Updated about 2 months ago.

Status:
New
Priority:
Normal
Assignee:
Category:
Enhancement to existing tests
Target version:
-
Start date:
Due date:
% Done:

0%

Estimated time:
Difficulty:

Description

Observation

#94714#note-7 shows a reminder message because there was no new build in Maintenance - QR - SLE15SP2 since nearly a month. In the meantime there is Maintenance - QR - SLE15SP3 with newer builds. I assume "QR - SLE15SP2" can be considered done so I moved the job group to "EOL". But why create a version-specific job group at all? I suggest to simplify the setup and just schedule all versions in the same job group which should reduce the work needed, e.g. also in the job templates needing less manual updating.

Actions

Also available in: Atom PDF