action #36694
open[sle15sp3][desktop] Implement test cases for gnome-software/gnome-package-kit/packagekit.
0%
Description
We have been lack of checking the packagekit mechanism in early development phase, and experienced some tough time to do a thorough check in the past.
Automating such a scenario on one hand will make sure the toolset is tested in early development, on the other hand, it will remind us update-test-*
should be ready in early development phase.
Notice the update-test-* packages will be intended to remove in GMC. So the case is supposed to be failed (or softfailed) in GMC build.
Updated by yfjiang almost 7 years ago
- Copied from action #36691: [sle12sp4][desktop] Implement test cases for gnome-package-kit/packagekit. added
Updated by yfjiang almost 7 years ago
- Subject changed from [sle15sp1][desktop] Implement openQA test case for gnome-software/gnome-package-kit/packagekit. to [sle15sp1][desktop] Implement test cases for gnome-software/gnome-package-kit/packagekit.
Updated by yfjiang almost 7 years ago
Potential overlaps from other tickets:
https://progress.opensuse.org/issues/36313
https://progress.opensuse.org/issues/35275
Updated by GraceWang over 3 years ago
- Subject changed from [sle15sp1][desktop] Implement test cases for gnome-software/gnome-package-kit/packagekit. to [sle15sp3][desktop] Implement test cases for gnome-software/gnome-package-kit/packagekit.
Updated by okurz over 3 years ago
This ticket was set to "High" priority but was not updated within the SLO period for "High" tickets (30 days) as described on https://progress.opensuse.org/projects/openqatests/wiki/Wiki#SLOs-service-level-objectives . Please consider picking up this ticket within the next 30 days or just set the ticket to the next lower priority of "Normal" (SLO: updated within 365 days). This update was done as agreed within the SUSE QE Sync call 2021-09-01
Updated by okurz over 3 years ago
- Priority changed from High to Normal
This ticket was set to "High" priority but was not updated within the SLO period for "High" tickets (30 days) as described on https://progress.opensuse.org/projects/openqatests/wiki/Wiki#SLOs-service-level-objectives . The ticket will be set to the next lower priority of "Normal".
Updated by slo-gin over 2 years ago
This ticket was set to Normal priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.
Updated by slo-gin 12 months ago
This ticket was set to Normal priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.