coordination #119314

closed

[epic] Milestone testing for SLE 15 SP5

Added by JERiveraMoya over 1 year ago. Updated 11 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
Start date:
2022-10-25
Due date:
2023-05-24
% Done:

100%

Estimated time:
(Total: 0.00 h)

Description

Motivation

As automated tests do not provide enough coverage and tests do not mutate, we as QA engineers want to assess risks of having issues in those parts of the product.

Please, see release schedule here: https://confluence.suse.com/display/SUSELinuxEnterpriseServer15SP5/Schedule


Subtasks 15 (0 open15 closed)

action #119317: SLE 15 SP5 Alpha-202210-3 Manual TestingResolvedgeor2022-10-25

Actions
action #119920: SLE 15 SP5 Beta1-202211 Manual TestingResolvedzoecao2022-11-04

Actions
action #119932: SLE 15 SP5 Beta1-202211 - RMT/SMT/SCC status check and milestone build triggeringResolvedzoecao2022-11-04

Actions
action #121543: SLE 15 SP5 Manual Testing Beta2-202212Resolvedgeor2022-12-06

Actions
action #121546: SLE 15 SP5 Beta2-202212 - RMT/SMT/SCC status check, milestone build triggering and reviewResolvedtinawang1232022-12-06

Actions
action #123337: SLE 15 SP5 Manual Testing Beta3-202301Resolvedgeor2023-01-19

Actions
action #123340: SLE 15 SP5 Beta3-202301- RMT/SMT/SCC status check, milestone build triggering and reviewResolvedrainerkoenig2023-01-19

Actions
action #124373: SLE 15 SP5 Manual Testing PublicBeta-202302Resolvedsyrianidou_sofia2023-02-13

Actions
action #124376: SLE 15 SP5 PublicBeta-202302 - RMT/SMT/SCC status check, milestone build triggering and reviewResolvedzoecao2023-02-13

Actions
action #125858: SLE 15 SP5 RC1-202303 - RMT/SMT/SCC status check, milestone build triggering and reviewResolvedzoecao2023-03-13

Actions
action #125861: SLE 15 SP5 Manual Testing RC1-202303Resolvedrainerkoenig2023-03-13

Actions
action #127808: SLE 15 SP5 PublicRC-202304 - RMT/SMT/SCC status check, milestone build triggering and reviewResolvedtinawang1232023-04-18

Actions
action #127811: SLE 15 SP5 Manual Testing PublicRC-202304Resolvedrainerkoenig2023-04-18

Actions
action #129053: SLE 15 SP5 Manual Testing GMC-202205Resolvedsyrianidou_sofia2023-05-122023-05-24

Actions
action #129059: SLE 15 SP5 GMC-202205 - RMT/SMT/SCC status check, milestone build triggering and reviewResolvedsyrianidou_sofia2023-05-19

Actions

Related issues 1 (0 open1 closed)

Related to qe-yam - coordination #121957: [saga] Consolidation of test coverage in Yam squadResolvedJERiveraMoya2022-03-25

Actions
Actions #1

Updated by JERiveraMoya over 1 year ago

  • Private changed from No to Yes
Actions #2

Updated by JERiveraMoya over 1 year ago

  • Subject changed from [Epic] Manual testing SLE 15 SP5 to [Epic] Milestone testing for SLE 15 SP5
  • Status changed from New to Workable
Actions #3

Updated by JERiveraMoya over 1 year ago

  • Private changed from Yes to No
Actions #4

Updated by JERiveraMoya over 1 year ago

  • Subject changed from [Epic] Milestone testing for SLE 15 SP5 to [epic] Milestone testing for SLE 15 SP5
  • Status changed from Workable to In Progress
Actions #5

Updated by JERiveraMoya over 1 year ago

Actions #6

Updated by JERiveraMoya 11 months ago

  • Status changed from In Progress to Resolved
Actions

Also available in: Atom PDF