Project

General

Profile

Actions

action #111171

closed

Handle installation of new FC switch size:M

Added by nicksinger over 2 years ago. Updated about 2 years ago.

Status:
Resolved
Priority:
Low
Assignee:
Category:
-
Start date:
2022-05-16
Due date:
% Done:

0%

Estimated time:

Description

Motivation

A new FC switch was ordered for the NetApp testing and should be installed as replacement for the older existing pantani-data-switch

## Suggestions

  • Switch needs to picked up from Reception (Iwona Maha)
  • It needs to be clarified where the switch needs to be, what connections, who will handle it etc.
    • Can be stored in the QA temporary storage
  • Connect and await feedback from common users, e.g. sebchlad and mmoese, if everything works as expected
Actions

Also available in: Atom PDF