Project

General

Profile

Actions

action #9512

closed

[opensuse] X-Desktop-Environment tests

Added by dimstar over 8 years ago. Updated almost 2 years ago.

Status:
Rejected
Priority:
Low
Assignee:
Category:
New test
Target version:
-
Start date:
2015-11-11
Due date:
% Done:

0%

Estimated time:
Difficulty:
Sprint:
QE-Core: April Sprint (Apr 13 - May 11)

Description

A distinguishing factor of openSUSE is our commitment to support multiple DEs on one machine.

We should at least do minimal testing to show that logging in the two major DEs (GNOME/Plasma) is possible from the 'other DEs' distinct login manager).

So:

  • Login to Plasma 5 from GDM
  • Login to GNOME 3 from SDDM

Checklist

  • TW
  • Leap
Actions #1

Updated by RBrownSUSE over 8 years ago

  • Category set to New test
  • Target version set to 160
Actions #2

Updated by RBrownSUSE over 8 years ago

  • Checklist item changed from to [ ] TW, [ ] Leap
  • Target version deleted (160)
Actions #3

Updated by okurz over 8 years ago

  • Description updated (diff)

I see this related to #9522, especially #9522#note-6 as I see an impact on how we handle the DESKTOP variable, also see https://github.com/os-autoinst/os-autoinst-distri-opensuse/pull/930#issuecomment-171219156 where coolo suggest

I guess we need to split into INSTALLDESKTOP and DESKTOP - where INSTALLDESKTOP is inherited for some values of DESKTOP.

Actions #4

Updated by okurz about 7 years ago

  • Subject changed from X-Desktop-Environment tests to [opensuse] X-Desktop-Environment tests

still a valid demand and still open

Actions #5

Updated by okurz over 2 years ago

  • Priority changed from Normal to Low

This ticket was set to "Normal" priority but was not updated within 730 days which is 2 times the period of the SLO for "Normal" tickets (365 days) as described on https://progress.opensuse.org/projects/openqatests/wiki/Wiki#SLOs-service-level-objectives . The ticket will be set to the next lower priority of "Low".

Actions #6

Updated by szarate almost 2 years ago

  • Status changed from New to Rejected
  • Assignee set to szarate

I think that in the meantime, this lost importance.

Actions #7

Updated by szarate almost 2 years ago

  • Sprint set to QE-Core: April Sprint (Apr 13 - May 11)
Actions

Also available in: Atom PDF