Project

General

Profile

Actions

action #69229

closed

coordination #42854: [functional][y][epic] Introduce relevant installation validation test modules

[y] Add validation to zfcp

Added by riafarov almost 4 years ago. Updated over 3 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
SUSE QA - SLE 15 SP3
Start date:
2020-07-22
Due date:
2020-09-22
% Done:

0%

Estimated time:
8.00 h

Description

We should validate zfcp device configuration. Normally we would have multipath enabled too, but as of now storage has only one device, so it should be based on ZFCP_ADAPTERS setting.

We might postpone work on this till we get multipath back and have 2 zfcp devices.
UPDATE: We actually have multipath enabled but for one channel, but we will get 4 devices one we have cables, like we have for old workers: https://openqa.suse.de/tests/4342166#step/disk_activation/12

See #69196 to reuse solution provided there to validate multipath configuration.

See zfcp_disk_configure, chccwdev, lszfcp tools which can be used for validation on top of standard set of tools.
https://www.ibm.com/support/knowledgecenter/linuxonibm/com.ibm.linux.z.ldsg/ldsg_t_step5configfcp.html
Also see "SCSI-over-Fibre Channel device driver"
https://www.ibm.com/support/knowledgecenter/en/linuxonibm/com.ibm.linux.z.lgdd/lgdd_r_scsifcp_dd.html
zfcp_ping, zfcp_show
https://www.ibm.com/support/knowledgecenter/linuxonibm/com.ibm.linux.z.ldsg/ldsg_r_hbautilities.html

Acceptance criteria

  1. zfcp disks configuration is validated
  2. multipath enablement is validated
  3. test data can be easily changed once we have 4 disks
Actions #1

Updated by riafarov over 3 years ago

  • Description updated (diff)
  • Status changed from New to Workable
  • Estimated time set to 8.00 h
Actions #2

Updated by riafarov over 3 years ago

  • Description updated (diff)
Actions #3

Updated by JRivrain over 3 years ago

  • Description updated (diff)
Actions #4

Updated by JERiveraMoya over 3 years ago

  • Assignee set to JERiveraMoya
Actions #5

Updated by JERiveraMoya over 3 years ago

  • Status changed from Workable to In Progress
Actions #6

Updated by JERiveraMoya over 3 years ago

  • Due date changed from 2020-09-08 to 2020-09-22

Still working in the PR, some assumption of fixed fields, like h:c:t:l were not correct.

Actions #7

Updated by JERiveraMoya over 3 years ago

  • Status changed from In Progress to Feedback
Actions #8

Updated by JERiveraMoya over 3 years ago

  • Status changed from Feedback to Resolved
Actions

Also available in: Atom PDF