Project

General

Profile

Actions

action #46700

closed

[opensuse][functional][y][sporadic] test fails in live_installation

Added by JRivrain over 5 years ago. Updated about 5 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
Category:
Bugs in existing tests
Target version:
SUSE QA - Milestone 23
Start date:
2019-01-25
Due date:
2019-02-12
% Done:

0%

Estimated time:
3.00 h
Difficulty:

Description

Observation

There is a right click menu that does not disappear in the installer window. It looks like an openqa bug.
It has been going on for about 2 months.
I could not reproduce this on a virtual machine (with the exact same image of course).

openQA test in scenario opensuse-15.0-KDE-Live-x86_64-kde-live_installation@64bit-2G fails in
live_installation

Test suite description

Live installer on KDE

Reproducible

Fails since (at least) Build 20.102

Expected result

Last good: 20.128 (or more recent)

Further details

Always latest result in this scenario: latest

Actions #1

Updated by okurz over 5 years ago

  • Due date set to 2019-02-26
  • Category set to Bugs in existing tests
  • Target version set to Milestone 23

JRivrain wrote:

Observation

There is a right click menu that does not disappear in the installer window. It looks like an openqa bug.
It has been going on for about 2 months.

Well, if it's an openQA bug then still we would need to investigate more. However, given that the operation of sending key events and mouse events to VMs works quite reliably in thousands of other tests I rather assume that the SUT is not receptive to the mouse event which is even more likely for "live systems" which can behave a bit slower, e.g. due to lower RAM that is available and such. Let's see if we can make that more stable.

Actions #2

Updated by riafarov about 5 years ago

  • Status changed from New to Workable
Actions #3

Updated by riafarov about 5 years ago

  • Estimated time set to 3.00 h
Actions #4

Updated by mloviska about 5 years ago

  • Due date changed from 2019-02-26 to 2019-02-12
  • Status changed from Workable to In Progress
Actions #5

Updated by mloviska about 5 years ago

Long time no see Leap-15.0 :D

Actions #6

Updated by mloviska about 5 years ago

  • Assignee set to mloviska
Actions #7

Updated by mloviska about 5 years ago

  • Status changed from In Progress to Feedback
  • Assignee deleted (mloviska)

PR:

20 VRs are currently in progress to validate test module stability:

Actions #8

Updated by mloviska about 5 years ago

  • Assignee set to mloviska
Actions #10

Updated by mloviska about 5 years ago

  • Status changed from Feedback to Resolved
Actions

Also available in: Atom PDF