coordination #130955

closed

coordination #121720: [saga][epic] Migration to QE setup in PRG2+NUE3 while ensuring availability

[epic] Migration out of SUSE NUE1 - QE setup in NUE3

Added by okurz 11 months ago. Updated 4 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
Start date:
2021-06-28
Due date:
% Done:

100%

Estimated time:
(Total: 0.00 h)

Description

Motivation

SUSE is deprecating NUE1 (Maxtorhof) and setting up replacement data centers. Primary location for production services will be PRG2 "Prg CoLo", see #121720. Additionally a new datacenter is planned as fail-over location

Acceptance criteria

  • AC1: NUE1 (Maxtorhof) is not relied upon by SUSE QE Tools anymore
  • AC2: Relevant SUSE QE Tools services are provided out of NUE3

Further details

Coordination chat room #dct-migration


Subtasks 7 (0 open7 closed)

openQA Infrastructure - action #94765: Bring openqaworker12 into production (w/o multi-machine test support) size:MRejectedokurz

Actions
openQA Infrastructure - action #94783: Bring openqaworker11 into production including multi-machine test support (same as w12) size:MRejected2021-06-28

Actions
openQA Infrastructure - action #95167: Bring openqaworker12 into production including multi-machine test supportRejectedokurz2021-07-07

Actions
action #131144: Decide about all LSG QE machines in NUE1 size:MResolvedokurz2023-06-20

Actions
action #132620: Move of selected LSG QE machines NUE1 to NUE3 size:MResolvedokurz2023-07-12

Actions
action #132623: Decommissioning of selected selected LSQ QE machines from NUE1-SRV2Resolvedokurz2023-07-12

Actions
openQA Infrastructure - action #132671: Ensure everybody in SUSE QE Tools knows how to access netbox size:MResolvedlivdywan2023-07-07

Actions