Status:
Resolved
Priority:
Normal
Assignee:
Category:
Bugs in existing tests
Target version:
SUSE QA - Milestone 30
Start date:
2020-09-22
Due date:
% Done:

0%

Estimated time:
42.00 h
Difficulty:

Description

Observation

This test is redundant, as the "hardware" variation doesn't really deserve the time invested in the review (as it is prone to failures)

The tests running in the gnome_sled scenario are mostly distributed across other test suites, however the main candidate to replace it, would be we-module, so we're dropping gnome_sled in favor of we-module in this case, and increasing the ram there, as we know already that systems running gnome under 2G will end up in a unstable system (see https://bugzilla.suse.com/show_bug.cgi?id=1166955)

openQA test in scenario sle-15-SP3-Online-x86_64-gnome_sled@laptop_64bit-virtio-vga fails in
system_prepare

Acceptance criteria

** AC1:** gnome_sled is unscheduled
** AC1:** we-module is running with 2GB of ram (use MACHINE=64bit-2gbram)

Reproducible

Fails since (at least) Build 42.1

Expected result

Last good: 36.5 (or more recent)

Further details

Always latest result in this scenario: latest

Actions #1

Updated by SLindoMansilla over 3 years ago

  • Description updated (diff)
Actions #2

Updated by szarate over 3 years ago

  • Description updated (diff)

The tests running in the gnome_sled scenario are mostly distributed across other test suites, however the main candidate to replace it, would be we-module, so we're dropping gnome_sled in favor of we-module in this case, and increasing the ram there, as we know already that systems running gnome under 2G will end up in a unstable system (see https://bugzilla.suse.com/show_bug.cgi?id=1166955)

Actions #3

Updated by szarate over 3 years ago

  • Description updated (diff)
Actions #4

Updated by szarate over 3 years ago

  • Description updated (diff)
Actions #6

Updated by SLindoMansilla over 3 years ago

  • Status changed from New to Workable
  • Target version set to Milestone 30
  • Estimated time set to 42.00 h
Actions #7

Updated by szarate over 3 years ago

  • Status changed from Workable to Feedback
  • Assignee set to szarate
Actions #8

Updated by szarate over 3 years ago

  • Status changed from Feedback to Resolved