Project

General

Profile

Actions

action #45830

closed

coordination #36712: [saga] Use YaST specific framework for GUI testing

coordination #43742: [functional][y][epic] Separate YaST UI framework to individual project

[functional][y] Split libyui-qt

Added by riafarov almost 6 years ago. Updated about 4 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
SUSE QA (private) - Milestone 23
Start date:
2019-01-08
Due date:
2019-03-26
% Done:

0%

Estimated time:
13.00 h

Description

See motivation in the parent ticket.

Acceptance criteria

  • Required changes to libyui-qt package are separated and only minimal changes are applied to libyui-qt itself
Actions #1

Updated by riafarov almost 6 years ago

  • Due date changed from 2019-01-29 to 2019-02-12
Actions #2

Updated by agraul almost 6 years ago

  • Category set to Enhancement to existing tests
Actions #3

Updated by okurz almost 6 years ago

  • Target version set to Milestone 22
Actions #4

Updated by riafarov almost 6 years ago

  • Due date changed from 2019-02-12 to 2019-02-26

ncurses still not yet split, moving to the next sprint.

Actions #5

Updated by riafarov almost 6 years ago

  • Due date changed from 2019-02-26 to 2019-03-12

same as before, still with ncurses

Actions #6

Updated by okurz almost 6 years ago

  • Target version changed from Milestone 22 to Milestone 23
Actions #7

Updated by riafarov almost 6 years ago

  • Status changed from New to Workable

Discussed with cwh, it makes sense that 2 persons do the split in parallel to share experience and try out different approaches.

Actions #8

Updated by riafarov almost 6 years ago

  • Assignee set to riafarov
  • Estimated time set to 13.00 h
Actions #9

Updated by riafarov almost 6 years ago

  • Due date deleted (2019-03-12)
Actions #10

Updated by riafarov almost 6 years ago

  • Due date set to 2019-03-26

I have spend ~4 hours on Monday and it's almost done, this sprint I do not plan to work on anything else (except SM responsibilities and mandatory activities out of scrum).

Actions #11

Updated by riafarov almost 6 years ago

  • Status changed from Workable to In Progress
Actions #12

Updated by riafarov almost 6 years ago

  • Status changed from In Progress to Feedback

All relevant PR mentioned here: https://github.com/libyui/libyui/pull/141

Actions #13

Updated by riafarov almost 6 years ago

  • Status changed from Feedback to Resolved

As being mentioned already, it's done. No feedback so far, so this part goes to #49430.

Actions

Also available in: Atom PDF