action #43658

closed

[sle][functional][u][s390x] re-enable extra_tests_on_gnome@s390x (or: Get vnc session working for SLE15SP1)

Added by zluo about 6 years ago. Updated over 4 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
Category:
Bugs in existing tests
Target version:
SUSE QA (private) - Milestone 30
Start date:
2018-11-12
Due date:
% Done:

0%

Estimated time:
42.00 h
Difficulty:

Description

Follow-up ticket from https://progress.opensuse.org/issues/34402

We need to fix vnc connection for sles 15 sp1 on s390. After that we can enable extra_tests_on_gnome@s390x at:
https://openqa.suse.de/admin/job_templates/139

Tasks

  1. Create YAML schedule for textmode test suite and remove any graphical test module from the schedule
  2. Create YAML schedule for gnome test suite and remove any textmode test module already covered by textmode test suite
  3. Make gnome test suite pass or fail on filed product bug

Further information


Related issues 1 (0 open1 closed)

Related to openQA Tests (public) - action #34402: [functional][u][s390x][medium] Revisit extra_tests_on_gnome@s390x (was: Do no run extra_tests_on_gnome on s390x)Resolvedzluo2018-04-062018-11-20

Actions
Actions #1

Updated by zluo about 6 years ago

  • Related to action #34402: [functional][u][s390x][medium] Revisit extra_tests_on_gnome@s390x (was: Do no run extra_tests_on_gnome on s390x) added
Actions #2

Updated by okurz about 6 years ago

  • Subject changed from [sle][functional][u][s390x] re-enable extra_tests_on_gnome@s390x when vnc session is working for sles 15 sp1 to [sle][functional][u][s390x] re-enable extra_tests_on_gnome@s390x (or: Get vnc session working for SLE15SP1)
  • Category set to Bugs in existing tests
  • Priority changed from Normal to Low
  • Target version set to future
Actions #4

Updated by szarate almost 5 years ago

  • Priority changed from Low to Normal
Actions #5

Updated by SLindoMansilla over 4 years ago

  • Description updated (diff)
Actions #6

Updated by SLindoMansilla over 4 years ago

  • Description updated (diff)
Actions #7

Updated by SLindoMansilla over 4 years ago

  • Description updated (diff)
Actions #8

Updated by zluo over 4 years ago

  • Status changed from New to In Progress
  • Assignee set to zluo
  • Target version changed from future to Milestone 31

let me check this at first.

Actions #9

Updated by zluo over 4 years ago

  • Status changed from In Progress to Resolved
  • Target version changed from Milestone 31 to Milestone 30
  • Estimated time set to 42.00 h

http://openqa.suse.de/tests/4357898
extra_tests_on_gnome is already there.

Actions

Also available in: Atom PDF