Description

Motivation

In current migration job group, the continues migration paths are:
SLES15 SP3 → SLES15 SP5→ SLES15 SP6
SLES15 SP4 → SLES15 SP5→ SLES15 SP6
This ticket is to adapt the above testsuites to the new migration paths:
SLES15 SP4 → SLES15 SP6→ SLES15 SP7
SLES15 SP5 → SLES15 SP6→ SLES15 SP7

So update the SLES15 SP3 → SLES15 SP5→ SLES15 SP6 to SLES15 SP4 → SLES15 SP6→ SLES15 SP7, and
update SLES 15SP4 → SLES15 SP5→ SLES15 SP6 to SLES15 SP5 → SLES15 SP6→ SLES15 SP7

That is to change the first phase of continues migration testsuites of [supp_migr_sles_15sp3_15sp5] to supp_migr_sles_15sp4_15sp6 in support images group.
And then update the second phase of continues migration testsuites of [migr_sles_continuous_15sp3_15sp5_ph1] to migr_sles_continuous_15sp4_15sp6_ph1 in migration job group.
And on ppc64le, all of the continues migration phases are in [migration daily group], adapt them as below:
Update migr_sles_continuous_15sp3_15sp5_phx to migr_sles_continuous_15sp4_15sp6_phx
Update migr_sles_continuous_15sp4_15sp5_phx to migr_sles_continuous_15sp5_15sp6_phx

Acceptance criteria

AC1 : Update the first phase of continues migration testsuites of [supp_migr_sles_15sp3_15sp5] to supp_migr_sles_15sp4_15sp6 in support images group.
AC2 : Update the second phase of continues migration testsuites of [migr_sles_continuous_15sp3_15sp5_ph1] to migr_sles_continuous_15sp4_15sp6_ph1 in migration job group.
AC3 : Adapt the continues migration jobs for ppc64le in migration job group also.