Motivation¶
In current migration job group, the continues migration paths are:
SLES15 SP3 → SLES15 SP5→ SLES15 SP6
SLES15 SP4 → SLES15 SP5→ SLES15 SP6
This ticket is to adapt the above testsuites to the new migration paths:
SLES15 SP4 → SLES15 SP6→ SLES15 SP7
SLES15 SP5 → SLES15 SP6→ SLES15 SP7
So update the SLES15 SP3 → SLES15 SP5→ SLES15 SP6 to SLES15 SP4 → SLES15 SP6→ SLES15 SP7, and
update SLES 15SP4 → SLES15 SP5→ SLES15 SP6 to SLES15 SP5 → SLES15 SP6→ SLES15 SP7
That is to change the first phase of continues migration testsuites of [supp_migr_sles_15sp3_15sp5] to supp_migr_sles_15sp4_15sp6 in support images group.
And then update the second phase of continues migration testsuites of [migr_sles_continuous_15sp3_15sp5_ph1] to migr_sles_continuous_15sp4_15sp6_ph1 in migration job group.
And on ppc64le, all of the continues migration phases are in [migration daily group], adapt them as below:
Update migr_sles_continuous_15sp3_15sp5_phx to migr_sles_continuous_15sp4_15sp6_phx
Update migr_sles_continuous_15sp4_15sp5_phx to migr_sles_continuous_15sp5_15sp6_phx
Acceptance criteria¶
AC1 : Update the first phase of continues migration testsuites of [supp_migr_sles_15sp3_15sp5] to supp_migr_sles_15sp4_15sp6 in support images group.
AC2 : Update the second phase of continues migration testsuites of [migr_sles_continuous_15sp3_15sp5_ph1] to migr_sles_continuous_15sp4_15sp6_ph1 in migration job group.
AC3 : Adapt the continues migration jobs for ppc64le in migration job group also.
Updated by openqa_review about 1 month ago
This is an autogenerated message for openQA integration by the openqa_review script:
This bug is still referenced in a failing openQA test: migr_sles_continuous_15sp3_15sp5_ph2
https://openqa.suse.de/tests/15613935#step/post_migration/1
To prevent further reminder comments one of the following options should be followed:
- The test scenario is fixed by applying the bug fix to the tested product or the test is adjusted
- The openQA job group is moved to "Released" or "EOL" (End-of-Life)
- The bugref in the openQA scenario is removed or replaced, e.g.
label:wontfix:boo1234
Expect the next reminder at the earliest in 28 days if nothing changes in this ticket.
Updated by JERiveraMoya about 1 month ago
- Tags set to qe-yam-oct-sprint
- Status changed from New to Workable
Updated by JERiveraMoya 30 days ago