action #160299

closed

coordination #151816: [epic] Handle openQA fixes and job group setup

self_update repos not ready for 15-SP6

Added by syrianidou_sofia about 2 months ago. Updated about 1 month ago.

Status:
Resolved
Priority:
High
Assignee:
Target version:
-
Start date:
2024-05-13
Due date:
% Done:

0%

Estimated time:

Description

Motivation

openQA test in scenario sle-15-SP6-Server-DVD-Updates-x86_64-qam-yast_self_update_plus_15@64bit fails in
validate_self_update and validate_self_update due to the self_update repos not containing any data yet.

Scope

The particular tests don't have a reason to run since there is no self_updates available. MR: https://gitlab.suse.de/qe-yam/openqa-job-groups/-/merge_requests/192 is removing the self update tests but they shoudl be re-enabled in the yast mu schedule, once the 15-SP6 self_update repos are functional.

Acceptance criteria

Actions #1

Updated by syrianidou_sofia about 2 months ago

  • Project changed from openQA Tests to qe-yam
  • Category deleted (Bugs in existing tests)
Actions #2

Updated by syrianidou_sofia about 2 months ago

  • Description updated (diff)
Actions #4

Updated by JERiveraMoya about 2 months ago

  • Tags set to qe-yam-may-sprint
  • Status changed from New to Workable
  • Priority changed from Normal to High
Actions #5

Updated by JERiveraMoya about 2 months ago

  • Parent task set to #151816
Actions #6

Updated by leli about 2 months ago

  • Status changed from Workable to In Progress
  • Assignee set to leli
Actions #8

Updated by leli about 2 months ago

MR submitted to remove +INSTALLER_SELF_UPDATE: '0 for 15SP6 MU test. https://gitlab.suse.de/qe-yam/openqa-job-groups/-/merge_requests/200

Actions #9

Updated by leli about 1 month ago

  • Status changed from In Progress to Resolved