Actions
action #137825
closedUrgent/Immediate tickets can only be in new/workable/progress/resolved - this needs to be mentioned in the wiki and also reflected in the backlog status
Updated by tinita about 1 year ago
- Copied from action #136007: Conduct "lessons learned" with Five Why analysis for network protocols failures on multimachine tests on HA/SAP size:S added
Updated by okurz about 1 year ago
- Status changed from New to In Progress
- Assignee set to okurz
- Target version changed from Tools - Next to Ready
Updated by livdywan about 1 year ago
- Status changed from In Progress to Workable
I'm afraid you can't work on this. We already have too many in progress.
Updated by okurz about 1 year ago
- Due date set to 2023-10-27
- Status changed from In Progress to Feedback
Updated by okurz about 1 year ago
- Due date deleted (
2023-10-27) - Status changed from Feedback to Resolved
https://os-autoinst.github.io/qa-tools-backlog-assistant/ has it, all done