Project

General

Profile

Actions

action #108368

open

[qe-core] Leap 15.4 test fails in enlightenment_first_start and shutdown re-working needed

Added by lkocman about 2 years ago. Updated about 1 month ago.

Status:
Feedback
Priority:
Normal
Assignee:
-
Category:
Bugs in existing tests
Target version:
-
Start date:
2022-03-15
Due date:
% Done:

0%

Estimated time:
Difficulty:

Description

Observation

Hello seems like there is some pending work on shutdown and first_start after our enlightenment update.
This is a tracker for the work.

I did ping Simon about it.

openQA test in scenario opensuse-15.4-NET-aarch64-otherDE_enlightenment@aarch64 fails in
enlightenment_first_start

Test suite description

Reproducible

Fails since (at least) Build 119.3

Expected result

Last good: (unknown) (or more recent)

Further details

Always latest result in this scenario: latest

Actions #1

Updated by szarate about 2 years ago

  • Subject changed from Leap 15.4 test fails in enlightenment_first_start and shutdown re-working needed to [qe-core] Leap 15.4 test fails in enlightenment_first_start and shutdown re-working needed
Actions #2

Updated by szarate about 2 years ago

Lubos, when you say that this is a tracker for the work I guess you mean the work to fix it? Also, is Simon (whoever that Simon is :)) going to work on fixing the tests?

Actions #3

Updated by szarate about 2 years ago

  • Status changed from New to Feedback
Actions #4

Updated by okurz about 2 years ago

szarate wrote:

Also, is Simon (whoever that Simon is :)) going to work on fixing the tests?

that would be "Simon Lees", maintainer of the enlightenment stack in openSUSE, also see
https://en.opensuse.org/Portal:Enlightenment/Team

Actions #5

Updated by openqa_review almost 2 years ago

This is an autogenerated message for openQA integration by the openqa_review script:

This bug is still referenced in a failing openQA test: otherDE_enlightenment
https://openqa.opensuse.org/tests/2349203#step/reboot_icewm/1

To prevent further reminder comments one of the following options should be followed:

  1. The test scenario is fixed by applying the bug fix to the tested product or the test is adjusted
  2. The openQA job group is moved to "Released" or "EOL" (End-of-Life)
  3. The bugref in the openQA scenario is removed or replaced, e.g. label:wontfix:boo1234

Expect the next reminder at the earliest in 32 days if nothing changes in this ticket.

Actions #6

Updated by slo-gin about 1 month ago

This ticket was set to Normal priority but was not updated within the SLO period. Please consider picking up this ticket or just set the ticket to the next lower priority.

Actions

Also available in: Atom PDF