Project

General

Profile

action #9758

schedule whole test group when scheduling individual but dependent test

Added by oholecek over 4 years ago. Updated over 4 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
-
Category:
Feature requests
Target version:
Start date:
2015-12-01
Due date:
% Done:

0%

Estimated time:
Difficulty:
Duration:

Description

If one use './client jobs post' to schedule individual job with START_AFTER_TEST or PARALLEL_WITH the parent test is not scheduled.

History

#1 Updated by RBrownSUSE over 4 years ago

  • Target version set to Milestone 1

#2 Updated by oholecek over 4 years ago

  • Status changed from New to Resolved

This was fixed by nadvornik - https://github.com/os-autoinst/openQA/pull/496

Difference is that you don't use jobs post but isos post with TEST variable set to limit scheduling to one individual test. Dependencies are then scheduled too.

Also available in: Atom PDF