Project

General

Profile

Actions

action #92185

closed

openQA Project (public) - coordination #80142: [saga][epic] Scale out: Redundant/load-balancing deployments of openQA, easy containers, containers on kubernetes

coordination #78206: [epic] 2020-11-18 nbg power outage aftermath

Our PowerPC worker machines need to be configured for automatic start after a power outage

Added by okurz over 3 years ago. Updated over 3 years ago.

Status:
Resolved
Priority:
Low
Assignee:
Category:
-
Start date:
2021-05-05
Due date:
% Done:

0%

Estimated time:

Description

Motivation

See parent #78206 . For all machines within osd and o3 with the exception of PowerPC workers we have enabled automatic start after a power outage. So for PowerPC we should still do that.

Acceptance criteria

  • AC1: All PowerPC machines within osd and o3 have been configured to automatically start after a power outage

Suggestions

For all other machines we already did that, see #80542#note-4 , but for PowerPC this does not work. So more research should be conducted or experts should be asked what can be done to do that or what to do instead.

Actions

Also available in: Atom PDF