closed

openQA Project - coordination #80142: [saga][epic] Scale out: Redundant/load-balancing deployments of openQA, easy containers, containers on kubernetes

coordination #78206: [epic] 2020-11-18 nbg power outage aftermath

Our PowerPC worker machines need to be configured for automatic start after a power outage

Added by okurz almost 3 years ago. Updated almost 3 years ago.

Status:
Resolved
Priority:
Low
Assignee:
Category:
-
Target version:
Start date:
2021-05-05
Due date:
% Done:

0%

Estimated time:

Description

Motivation

See parent #78206 . For all machines within osd and o3 with the exception of PowerPC workers we have enabled automatic start after a power outage. So for PowerPC we should still do that.

Acceptance criteria

  • AC1: All PowerPC machines within osd and o3 have been configured to automatically start after a power outage

Suggestions

For all other machines we already did that, see #80542#note-4 , but for PowerPC this does not work. So more research should be conducted or experts should be asked what can be done to do that or what to do instead.