Project

General

Profile

Actions

action #2562

closed

action #2520: Implement Factory-Tested Manager

Implement actual work flow of the tested manager

Added by coolo over 10 years ago. Updated over 10 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
Start date:
2014-05-26
Due date:
% Done:

100%

Estimated time:
10.00 h

Description

As this involves a lot of testing and reiterating, I set the estimated time pretty high

Actions

Also available in: Atom PDF