Project

General

Profile

Actions

action #2562

closed

action #2520: Implement Factory-Tested Manager

Implement actual work flow of the tested manager

Added by coolo almost 10 years ago. Updated almost 10 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
Start date:
2014-05-26
Due date:
% Done:

100%

Estimated time:
10.00 h

Description

As this involves a lot of testing and reiterating, I set the estimated time pretty high

Actions #1

Updated by coolo almost 10 years ago

  • Status changed from New to In Progress
  • Assignee set to coolo
  • Target version set to Staging sprint 09
Actions #2

Updated by coolo almost 10 years ago

  • % Done changed from 0 to 70
Actions #3

Updated by coolo almost 10 years ago

  • Status changed from In Progress to Resolved
  • % Done changed from 70 to 100
Actions

Also available in: Atom PDF