action #134822

closed

QA - coordination #121720: [saga][epic] Migration to QE setup in PRG2+NUE3 while ensuring availability

QA - coordination #123800: [epic] Provide SUSE QE Tools services running in PRG2 aka. Prg CoLo

Migration of osd VM to PRG2 - Decommission old-osd in NUE1 as soon as we do not need it anymore size:M

Added by okurz 9 months ago. Updated 8 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
Category:
-
Target version:
Start date:
2023-08-30
Due date:
% Done:

0%

Estimated time:
Tags:

Description

Motivation

The openQA webUI VM for osd was moved to PRG2. We should clarify that we don't need the old anymore and then decommission it.

Acceptance criteria

  • AC1: osd openQA jobs run successfully for all four archs x86_64+aarch64+s390x+ppc64le without relying on old-osd
  • AC2: old-osd has been deleted
  • AC3: All references to old-osd are removed, e.g. racktables

Suggestions

  • DONE Wait for #133364 to proceed sufficiently
  • DONE Switch off services on old OSD to see if people relied upon it, e.g. based on manual IP
  • DONE Switch off the VM
  • DONE Ask Eng-Infra to decommission old-osd for good
  • Ensure that references to old-osd are removed, e.g. racktables

Related issues 1 (0 open1 closed)

Copied from openQA Infrastructure - action #133364: Migration of o3 VM to PRG2 - Decommission old-ariel in NUE1 as soon as we do not need it anymoreResolvedokurz