Project

General

Profile

Actions

action #133706

closed

coordination #121720: [saga][epic] Migration to QE setup in PRG2+NUE3 while ensuring availability

coordination #129280: [epic] Move from SUSE NUE1 (Maxtorhof) to new NBG Datacenters

Setup of former QAM machines from NUE1-SRV2 in FC Basement

Added by okurz 10 months ago. Updated 9 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
Start date:
2023-08-02
Due date:
% Done:

0%

Estimated time:

Description

Motivation

Within #132614 many former QAM machines have been moved to FC Basement which should be reviewed and setup accordingly.

Acceptance criteria

  • AC2: All LSQ QE machines which are former QAM machines are usable as in before

Suggestions

  • Wait for #132614
  • Review each and every machine and put those in production that are needed for now, store the others
Actions

Also available in: Atom PDF