Project

General

Profile

Actions

report #133

closed

openSUSE Release report

Added by toscalix about 11 years ago. Updated over 10 years ago.

Status:
Closed
Priority:
High
Assignee:
toscalix
Category:
Management
Target version:
Start date:
2013-03-19
Due date:
2013-06-10
% Done:

100%

Estimated time:
(Total: 13.00 h)

Description

After every Release, a written report is sent to the Department Lead and the Engineering VP. This report contains the following item:

  • Introduction
  • Description ** Milestones and major tasks ** Description of the major tasks executed ** Impact ** References ** Financial report
  • Analysis ** Go through every description item and analize what went wrong and right ** Final Conclusions. Done by the Team Lead, it summarizes the individual and team analisys
  • Recommendations ** Recommendations for next Release and for managers

For guidance, check 12.2 report

openSUSE Team creates and internal report and send the Board a version of it.

https://wiki.innerweb.novell.com/index.php/OpenSUSE_team_report_12.3


Subtasks 4 (0 open4 closed)

action #199: Download numbersClosedaplanas2013-03-192013-05-06

Actions
action #200: Numbers of hits in websClosedaplanas2013-03-192013-03-22

Actions
action #201: Update of the social media dataClosed2013-03-192013-05-06

Actions
report #472: openSUSE 12.3 report Feedback Closedtoscalix2013-05-272013-06-10

Actions
Actions #1

Updated by toscalix about 11 years ago

  • Start date changed from 2013-03-06 to 2013-03-14
Actions #2

Updated by toscalix about 11 years ago

  • % Done changed from 0 to 10
  • Status changed from New to In Progress

Talked about it during the Milestone meeting, specially to cwh, so he prepare a plan for openQA

Actions #3

Updated by lnussel about 11 years ago

  • Description updated (diff)
Actions #4

Updated by toscalix about 11 years ago

  • % Done changed from 10 to 0
  • Due date changed from 2013-03-20 to 2013-03-22
  • Estimated time changed from 30.00 h to 5.00 h
  • Start date changed from 2013-03-14 to 2013-03-19
Actions #5

Updated by toscalix about 11 years ago

  • Estimated time changed from 5.00 h to 9.00 h
Actions #6

Updated by toscalix about 11 years ago

  • Estimated time changed from 9.00 h to 11.00 h
Actions #7

Updated by aplanas about 11 years ago

  • % Done changed from 0 to 32
Actions #8

Updated by Anonymous about 11 years ago

  • % Done changed from 32 to 45
Actions #9

Updated by lnussel about 11 years ago

  • % Done changed from 45 to 58
Actions #10

Updated by toscalix about 11 years ago

When Alberto comes back, he need to update the 1 month after the release data. The report will be finished next week (Friday) as deadline.

Actions #11

Updated by toscalix almost 11 years ago

  • % Done changed from 58 to 73
Actions #12

Updated by toscalix almost 11 years ago

  • % Done changed from 73 to 59
Actions #13

Updated by toscalix almost 11 years ago

  • Due date changed from 2013-03-22 to 2013-05-06
Actions #14

Updated by Anonymous almost 11 years ago

  • % Done changed from 59 to 65
Actions #15

Updated by aplanas almost 11 years ago

  • % Done changed from 65 to 78
Actions #16

Updated by aplanas almost 11 years ago

  • % Done changed from 78 to 100
Actions #17

Updated by toscalix almost 11 years ago

Done the first attempt for conclusions and recommendations. Tomorrow I will go over it again. Waiting for feedback from team members.

Actions #18

Updated by toscalix almost 11 years ago

  • Status changed from In Progress to Resolved
  • Extended version of the 12.3 Report done.
  • Executive report done
  • Spell check done.
  • Formatting and sending done.
Actions #19

Updated by toscalix almost 11 years ago

Waiting for Roland to give me feedback

Actions #20

Updated by toscalix almost 11 years ago

  • % Done changed from 100 to 86
  • Due date changed from 2013-05-06 to 2013-06-10
  • Estimated time changed from 11.00 h to 13.00 h
Actions #21

Updated by toscalix over 10 years ago

  • Status changed from Resolved to Closed
Actions