[tools][metrics] Improve cycle + lead times in Grafana

Added by tinita over 1 year ago. Updated 11 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
Start date:
Due date:
% Done:

0%

Estimated time:

Description

Motivation

In #121582 we added statistics from our backlog to Grafana:

  • Ticket counts of the different backlog queries
  • Cycle & lead times

The cycle and lead times are reported in a way that we can calculate the mean times, but not median.
It was requested that we support median.
Also it should be possible to feed data for a certain time frame to Grafana, e.g. when we change something in the calculation, or the Grafana database is gone, or we simply want to import historical data. Ideally this script can be used by other teams as well.

Acceptance criteria

  • AC1: Grafana graphs for cycle and lead time based on the median instead of mean are available

Suggestions

  • Find out why in https://github.com/openSUSE/backlogger/blob/main/backlogger.py#L198 it was chosen to calculate the mean value instead of just feeding all raw values directly to grafana?
  • Extract the leadTime calculation from the backlogger script, because the original backlog status page script doesn't need this, and it will make it easier to add new options that don't make much sense for the backlogger
  • Refactor/split up the code to avoid copying logic/config data if that makes sense (unless it's more work and not worth the effort)
  • Use the same codebase since other teams can also benefit from this effort
    • Metrics can be computed based on an option for a certain timeframe
    • Metrics still include data for the last day by default
    • Metrics include data for each individual ticket, so we can calculate the median in Grafana
  • Read up what median is and how to compute it :-D
  • MAke this an additional feature that can be used at the same time (so we can compare both accurately based on real data)

Files


Related issues 2 (0 open2 closed)

Related to openQA Project (public) - action #152957: Weekly evaluation of cycle-times within SUSE QE Tools size:SResolvedlivdywan2023-12-28

Actions
Copied from QA (public) - action #121582: [tools][metrics] Calculate cycle + lead times for SUSE QE Tools continuously size:MResolvedlivdywan2022-12-062023-03-31

Actions
Actions #1

Updated by tinita over 1 year ago

  • Copied from action #121582: [tools][metrics] Calculate cycle + lead times for SUSE QE Tools continuously size:M added
Actions #2

Updated by tinita over 1 year ago

  • Description updated (diff)
Actions #3

Updated by okurz over 1 year ago

  • Target version set to future
Actions #4

Updated by okurz over 1 year ago

  • Description updated (diff)
Actions #5

Updated by okurz 12 months ago

  • Target version changed from future to Ready
Actions #6

Updated by livdywan 11 months ago

  • Description updated (diff)
  • Status changed from New to Workable
Actions #7

Updated by tinita 11 months ago

  • Description updated (diff)
Actions #8

Updated by okurz 11 months ago

  • Status changed from Workable to In Progress
  • Assignee set to okurz

tinita and me discussed this in detail and we found that we should be able to work with the values that are written from backlogger.py but that we can just change how values are evaluated and displayed in grafana

Actions #10

Updated by okurz 11 months ago

or if we want to go more fancy

after_10d_30d_trend_lines.png

with logarithmic scale and trend lines

Actions #11

Updated by openqa_review 11 months ago

  • Due date set to 2024-01-26

Setting due date based on mean cycle time of SUSE QE Tools

Actions #12

Updated by okurz 11 months ago

  • Status changed from In Progress to Feedback

https://gitlab.suse.de/openqa/salt-states-openqa/-/merge_requests/1080 merged. Waiting for feedback from team regarding latest proposal.

Actions #14

Updated by okurz 11 months ago

  • Due date deleted (2024-01-26)
  • Status changed from Feedback to Resolved

merged. While with the current technical approach only an averaged mean value is shown I still think those values produce something that helps us. We always assumed a cycle time of 14 (calendar) days. The cycle time that we compute has an average value of around 5-6 calendar days. That is because in our calculation in backlogger.py we only really count the time when a ticket is "In Progress" so any waiting time in between when setting to any other state, e.g. "Workable" or "Feedback" don't count towards that. But actually I think we can also work with that knowing our way to calculate.

Actions #15

Updated by okurz 11 months ago

  • Related to action #152957: Weekly evaluation of cycle-times within SUSE QE Tools size:S added