Motivation¶
For new product SLE-15-SP5 we need to setup configuration for scenarios which migrate from SLE-15-SP4.
List of offline scenarios to add for x86_64:
SLES:
SLED (all will change to python3):
Acceptance criteria¶
AC1: Setup offline x86_64 scenarios which migrate from SLE-15-SP4 in 'Migration' and 'Migration: Milestone' job groups
AC2: File proper bugs if you find any issues
Suggestions¶
Configuration should be very similar to SLE-15-SP3, only some scenarios are moved to 'Milestone' job group as we run more combination in this job group for newer products. Also we do variations adding all patterns.
Check migration matrix
- Description updated (diff)
JERiveraMoya wrote:
Motivation¶
For new product SLE-15-SP5 we need to setup configuration for scenarios which migrate from SLE-15-SP4.
List of offline scenarios to add for x86_64:
SLES:
Migration daily group:
Migration Milestone group:
SLED (all will change to python3):
Update the SLED part here (I can not edit the ticket's description) :
For SLED, need to convert the SLED-15-SP3 to SLED-15-SP4 in the cases setting and cases name. (all will change to python3)
Migration daily group:
- G105: Convert offline_sled15sp3_media_basesys-desk-we-dev-python2_all_full
- G106: Convert offline_sled15sp3_pscc_basesys-desk-we-phub-python2_def_full
Migration Milestone group:
- G103: Convert offline_sled15sp3_rmt_basesys-desk-we-python2_all_full
- G102: Convert offline_sled15sp3_scc_basesys-desk-we-python2_def_full
Acceptance criteria¶
AC1: Setup offline x86_64 scenarios which migrate from SLE-15-SP4 in 'Migration' and 'Migration: Milestone' job groups
AC2: File proper bugs if you find any issues
Suggestions¶
Configuration should be very similar to SLE-15-SP3, only some scenarios are moved to 'Milestone' job group as we run more combination in this job group for newer products. Also we do variations adding all patterns.
Check migration matrix
- Tags deleted (
qe-yast-refinement)
- Status changed from New to Workable
- Status changed from Workable to In Progress
- Assignee set to zoecao
- Status changed from In Progress to Resolved
MR is merged, so resolve the ticket now.