Project

General

Profile

Actions

action #114727

open

[QE-SAP] remove 3 nodes tests

Added by emiura over 1 year ago. Updated over 1 year ago.

Status:
New
Priority:
Normal
Assignee:
Category:
-
Target version:
-
Start date:
2022-07-27
Due date:
% Done:

0%

Estimated time:

Description

Not all tests support 3nodes testing (for example, drbd). Also, it appears to be redundant since we already have 2 nodes cluster tests.

Actions #2

Updated by acarvajal over 1 year ago

emiura wrote:

Not all tests support 3nodes testing (for example, drbd). Also, it appears to be redundant since we already have 2 nodes cluster tests.

Yes, drbd test is designed only for 2-node clusters as it's a master/slave resource, but I don't think the way to go is to remove the whole scenario (3 node cluster) but the test itself. I am working on a PR for this, will update when I submit it.

dzedro wrote:

https://gitlab.suse.de/qa-css/openqa_ha_sap/-/merge_requests/365

Let's wait before merging this. If we drop the 3 node scenario we could be decreasing test coverage (for example when there's a MU for crmsh), so I think better to leave the scenario and take out the drbd_passive test module.

Actions #3

Updated by acarvajal over 1 year ago

Submitted https://github.com/os-autoinst/os-autoinst-distri-opensuse/pull/15324 to fix.

Verification runs still ongoing.

Actions #4

Updated by acarvajal over 1 year ago

https://github.com/os-autoinst/os-autoinst-distri-opensuse/pull/15324 merged. I am closing this ticket. Re-open if issue appears again. Seems I cannot close it. I leave that to you @emiura.

Actions

Also available in: Atom PDF