Added by dimstar about 9 years ago. Updated about 9 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
-
Target version:
Start date:
2015-10-30
Due date:
2015-11-03
% Done:

100%

Estimated time:

Description

the test updates need to be removed from the update channel at some point before GA. Ask opensuse-maintenance@opensuse.org


Related issues 2 (0 open2 closed)

Copied from openSUSE 13.2 Release - action #4192: ask maintenance to remove the test updatesResolveddimstar2014-11-032014-11-04

Actions
Copied to openSUSE Leap 42.2 Release - action #13336: ask maintenance to remove the test updatesClosed2016-11-152016-11-15

Actions
Actions #1

Updated by dimstar about 9 years ago

  • Copied from action #4192: ask maintenance to remove the test updates added
Actions #2

Updated by dimstar about 9 years ago

During test phases, we needed some test updates to get the update stack tested - Ask maintenance to wipe the test updates, to get to a clean start

Actions #3

Updated by lnussel about 9 years ago

  • Due date set to 2015-11-03
  • Target version set to GA
  • Start date set to 2015-10-30
Actions #4

Updated by Neyleah about 9 years ago

  • Status changed from New to Resolved
  • % Done changed from 0 to 100

This is already done by Benni

Actions #5

Updated by lnussel about 8 years ago

  • Copied to action #13336: ask maintenance to remove the test updates added