Motivation¶
During the last "power outage" in Nbg data center we fared kinda ok but some machines and services did not come up by themselves due to simple things, e.g. not being configured to automatically power on after power is restored. See #78206 for details
Acceptance criteria¶
- AC1: We have a schedule within the team SUSE QE Tools when we forcefully shut down all or selected systems to test our recovery plans
- AC2: A simple requirements catalog for our services is listed what we need to ensure in service designs
Suggestion¶
- Decide about a useful cadence, date and procedure