Description
Check other project categories and add them to this project
History
#1
Updated by toscalix about 9 years ago
- Category set to Administration
- % Done changed from 0 to 90
- Status changed from New to Feedback
I did it, please check it and Resolve the task if you agree
#2
Updated by aplanas about 9 years ago
- Status changed from Feedback to Closed
#3
Updated by aplanas about 9 years ago
- % Done changed from 90 to 100
#4
Updated by aplanas about 9 years ago
- Estimated time set to 8.00 h