Observation¶
While working on #180989 we noticed that the IPMI tests do not return a shutdown state, for example here.
See latest, in case the job was deleted
[2025-04-23T18:06:42.417633Z] [debug] [pid:169492] backend shutdown state:
ususally it should return a boolean value, like seen here:
[2025-05-02T10:13:11.249236Z] [debug] [pid:32803] backend shutdown state: 1
Updated by okurz about 8 hours ago
- Tags changed from infra, ipmi to ipmi
- Project changed from openQA Infrastructure (public) to openQA Project (public)
- Category deleted (
Regressions/Crashes)
Updated by okurz about 8 hours ago
- Related to action #180989: [openQA][worker][ipmi] ipmi jobs are stuck in tear-down and run into MAX_JOB_TIME (was: It takes an extremely long time to finish the job when connected to an ipmi worker) size:S added