action #1479

staging accept needs to accept into Factory

Added by coolo over 6 years ago. Updated over 6 years ago.

Status:
Resolved
Priority:
High
Assignee:
-
Target version:
Start date:
2014-02-12
Due date:
% Done:

0%

Estimated time:

Description

As staging prjs are the new groups now, we need to make sure we accept things together. So accept needs to:

  • ACK the review (factory-staging for now, by_project later)
  • accept the requests into factory
  • add additional packages into the ring projects (no meta data for that yet)
  • cleanup the packages from staging prj - including meta data
  • build disable the prj

History

#1 Updated by coolo over 6 years ago

  • Status changed from New to In Progress
  • Priority changed from Normal to High

as right now accept is removed completely, this became an urgent issue :)

#2 Updated by coolo over 6 years ago

  • Target version set to Staging sprint 2

#3 Updated by coolo over 6 years ago

  • Status changed from In Progress to Resolved

Also available in: Atom PDF