## Motivation 
 NUE1 needs to be emptied. For some machines we opted to have them moved to "PRG2e" aka. "PRG2 Colo Extension" or similar. Assuming nobody does the job for us we need to unrack and organize the move with Facilities and SUSE-IT. 

 ## Acceptance criteria 
 * **AC1:** All machines from https://netbox.suse.de/dcim/devices/?tag=qe-lsg&tag=move-to-prague-colo2 are usable from PRG2e 

 ## Suggestions 
 * Ask hreinecke and SUSE-IT and wengel and others how this move is organized 
 * As necessary organize transport of equipment: Create ticket over https://sd.suse.com to component "Facilities" asking them how and where to prepare machines for move and ask them to move the equipment to FC Basement 
 * As necessary: Go to NUE1 Maxtorhof place beforehand and prepare the move, e.g. nothing connected anymore, put on pallet, labeled, packed into boxes, etc. 
 * Inform users about the pending move 
 * Ensure machines are usable from PRG2e 
 * Ensure documentation is up-to-date 
 * Inform users after everything is done 

 ## Rollback steps 
 Remove alert silence from https://monitor.qa.suse.de/alerting/silences with `alertname=openqaw5-xen: host up alert`