## Motivation 
 Rent at Maxtorhof will end. The new location at Nbg Frankencampus will have lab rooms in the same building where the office rooms are. We must prepare and execute the move of QAM equipment from the old location, mostly [NUE-2.2.10 QA cold storage](https://racktables.nue.suse.com/index.php?page=row&row_id=18018) to an according Frankencampus room 

 ## Acceptance criteria 
 * **AC1:** There is no more QAM equipment in Maxtorhof office rooms or [NUE-2.2.10](https://racktables.nue.suse.com/index.php?page=row&row_id=18018) 
 * **AC2:** Racktables is up-to-date 

 ## Suggestions 
 * Ask for objections 
 * Organize transport of still usable equipment: Create ticket over https://sd.suse.com to component "Facilities" asking them to handle the disposal 
 * Scrap equipment and scrapping decommissioned hardware, see https://wiki.suse.net/index.php/SUSE-Quality_Assurance/Labs#How_to_decommission_and_dispose_old_hardware 

 ## Further details hardware 
 The above tasks shouldn't need anyone from our team on-site