action #111473
Updated by okurz over 2 years ago
## Motivation
Move to co-location is delayed, we need to keep O3+OSD infrastructure within NUE SRV1 up-to-date.
## Acceptance criteria
* **AC1:** Updated the two oldest workers in NUE SRV1 (imagetester+openqaworker1)
## Suggestions
* We need to make physical space for new machines (might be possible to remove uno+rebel or openqaworker2+openqaworker3 to make room)
* Get the quote from Nick or Oli
* DONE: Get a quote, e.g. from https://www.deltacomputer.com/ for supermicro machines to replace at least imagetester+openqaworker1, potentially also uno+rebel or openqaworker2+openqaworker3 -> https://www.deltacomputer.com/media/pdf/delta_d10z-m2-zm_0465.pdf
* Clarify ownership and usage of [uno.openqanet.opensuse.org](https://racktables.nue.suse.com/index.php?page=object&tab=default&object_id=680)
* Bring the order forward to ~~Lee Martin~~ Nick Singer and Matthias Grießmeier to crosslink with the QE budget
* Coordinate with SUSE-IT EngInfra to prepare for new machines replacing existing ones
* Make sure machines are ordered to SUSE Nbg Maxtorhof
* Ask SUSE-IT EngInfra if it's ok if we sponsor a new top-of-the-rack switch with 10G SFP to replace the existing one https://racktables.nue.suse.com/index.php?page=object&object_id=163 in NUE-SRV1-D-6
## Further details
Suggested by nsinger:
* Chassis 1x SuperMicro 825BTQC-R1K23LPB
* RAM 8x Micron MTA36ASF8G72PZ-3G2: 512 GB
* Disk 2x Samsung PM1643a 3,8TB SSD
* Controller 1x Broadcom 9500-8i
* Network 1x Intel X710-DA2, 2 Ports, 10GbE, SFP+
* M.2 NVMe, 2x Micron 7400 MAX, 400 GB, SSD
* CPU 1x AMD EPYC 7763, 64 Cores pro CPU, 2,45 GHz