action #468

action #394: Publish announcement of Milestone 1

communicate M1 and schedule internally

Added by Anonymous almost 7 years ago. Updated over 6 years ago.

Status:ClosedStart date:16/05/2013
Priority:NormalDue date:17/05/2013
Assignee:-% Done:

100%

Category:Marketing
Target version:13.1 Milestone 1
Duration: 2

Description

Mail announcement out internally in SUSE, pointing to both the schedule for 13.1 and that M1 is out.

History

#1 Updated by Anonymous over 6 years ago

  • Status changed from New to In Progress

Better late than never: this fell off my radar, I did it today.

#2 Updated by Anonymous over 6 years ago

  • % Done changed from 0 to 100
  • Status changed from In Progress to Resolved

And done:

"Milestone 1 is out, have you checked in your packages yet?" to devel, research and internal.

#3 Updated by lnussel over 6 years ago

  • Status changed from Resolved to Closed

Also available in: Atom PDF