Test cases migrate and maintain guideline¶
Overall test case structure¶
Acceptance testing¶
- We will have a parent task for all acceptance test cases: https://progress.opensuse.org/issues/117445
- We will add sub tasks under the parent task
Regression testing¶
- We will have a parent task for all regression test cases: https://progress.opensuse.org/issues/117442
- We will use category to mark if the test case has already been automated
- We will use parent-sub task mode to mark the specific component
- We will use the target version field to mark which release we are testing
The format of the subject¶
- The subject should be started with [Regression] OR [Acceptance]
For [Regression] test cases, the second key word should be the component of the test case, e.g [NetworkManager]
For [Acceptance] test cases, the second and third key word should be the exact milestone and build number. e.g [Alpha4][151.1]
- The priority of the ticket
P0 -> Immediate
P1 -> Urgent
P2 -> High
P3 -> Normal
P4 -> Low
The status of the ticket/ test case:¶
- The default of the test case is NEW
- The test case will be marked as RESOLVED when test passed,
- The test case will be marked as REJECTED if there's any critical bugs found
- The corresponding SUT build number should be included in the comment when updating the status
Test preparation¶
- Before regression test execution, we always clone the regression test tickets used by the last release as a base for the upcoming release.
- Before acceptance test execution for each milestone, we clone acceptance tickets from https://progress.opensuse.org/issues/116974